Typical SMT Machine changeover times?

Electronics Forum | Thu Mar 30 06:32:17 EST 2006 | smartasp

Wow Frank You guys must be assemblyng overengineered Gaming machine boards. You beat me. My definition of quality is fit for purpose and thats the criteria we select our equipment. I suppose the Juki does exactly for you what you need. Still the fel

Typical SMT Machine changeover times?

Electronics Forum | Fri Mar 24 17:04:28 EST 2006 | kevslatvin

We are looking into uprgading our current pick and place machine which is a very entry level machine with a higher class or more production oriented machine. On our current machine change over is fairly slow. I was wanting to know if any users of the

Typical SMT Machine changeover times?

Electronics Forum | Wed Mar 29 09:40:26 EST 2006 | kevslatvin

Thanks for the replies.With which ever machine we decide on the feeders with the most commonly used parts will stay on the machine. Also parts used on other jobs but not needed for the current one will be able to stay as well. The problem well run in

Typical SMT Machine changeover times?

Electronics Forum | Wed Mar 29 11:42:20 EST 2006 | Frank

Since you are a HM/LV facility take a look at the feeder design. I noticed that the MyData feeders (that I have seen) peel back a lot of pockets before the pick, so when you change part numbers on the feeder there is a larger waste of components. O

Typical SMT Machine changeover times?

Electronics Forum | Wed Mar 29 03:40:06 EST 2006 | Frank

The Juki 2060 can have both front and rear trolleys and you do not loose any feeder locations. My question was why can't the Assembleon put trolley on the rear? I recently visited a friend at a company that used a lot of Assembleon and compared run

Best practices for changeover --Leaded > Lead-free > Leaded--

Electronics Forum | Tue Dec 02 18:29:23 EST 2014 | jorge_quijano

Hola, here is a question that may be answered by common sense, but I'd like to hear from you; I have a couple of SMT lines, and I'm constantly changing from leaded to lead-free process and backwards, so, I cannot dedicate one line for leaded and ano

Matrix/Jedec tray changeover at pick and place surface mount.

Electronics Forum | Tue Oct 12 13:03:18 EDT 2021 | cunningham

Afternoon all, Do you use any special surface other that ESD matting when changing over matrix trays? We currently use a earthed wire trolley that we keep trays and MSD bags on and when replenishing stock its carried out on the trolley. Does anyon

Best practices for changeover --Leaded > Lead-free > Leaded--

Electronics Forum | Tue Dec 16 22:09:36 EST 2014 | deanm

The critical operations where cross contamination can occur is the paste printer, the touch up station and the hand soldering station. Hand insertion should not be a problem if the parts are kitted or issued with proper control. If possible I would

Product Changeover (SMT double sided)

Electronics Forum | Sun Oct 28 14:06:06 EST 2001 | kenbliss

Hi Paul There is free detailed information on how to reduce changeover time and to reduce bottlenecks on our web site at http://www.blissindustries.com then click on Bliss University, it is written as unbiased information on reducing down time du

Wave Changeover-Hints -Tips?

Electronics Forum | Mon May 15 08:53:52 EDT 2006 | aj

Hi All, Due to carry out the Bath Changeover this weekend. I have an Electrovert Econopak- 550 kg bath. We are not replacing our internal components i.e nozzles/pumps etc. until we really have to. Has anyine carried out there changeover yet and ha


changeover searches for Companies, Equipment, Machines, Suppliers & Information

Thermal Interface Material Dispensing

High Precision Fluid Dispensers
Selective soldering solutions with Jade soldering machine

Have you found a solution to REDUCE DISPENSE REWORK? Your answer is here.
Selective soldering solutions with Jade soldering machine

Wave Soldering 101 Training Course
Pillarhouse USA for handload Selective Soldering Needs

High Throughput Reflow Oven