SMT Line Performance Measurement

Electronics Forum | Wed Oct 28 13:29:09 EDT 2020 | davef

Back in the old days, based on "The Goal" by Eliyahu Goldratt, we wanted to optimize throughput. In this ... * THE GOAL: Make more money. Increase throughput. Make more money. * Throughput is gated by the bottleneck. * Bottleneck is where the mate

Downtime Calculation

Electronics Forum | Sat Aug 17 07:34:36 EDT 2002 | bentzen

Hi Ken First of all, I think you are right to point out that the uptime should be calculated on the SMD line bottleneck. But I have some comments to your posting in general: The SMD line bottleneck, you say, is always the palcement machine. This i

Downtime Calculation

Electronics Forum | Sat Aug 17 07:48:43 EDT 2002 | bentzen

Hi Brandon. You should always try to optimize / "balance" your line in a way so the machine with the shortest time per placement is your bottleneck. The other machines in the line should then have a 10 - 20 sec sorter cycle time, to be able to cope

How to run SMT production with low defects

Electronics Forum | Thu Aug 15 13:36:44 EDT 2002 | kenbliss

I would take the following method to start Which defect is taking the most labor time to fix. which defect is causing a bottleneck to your production. Fix the one causing the bottleneck first as it will improve your plant output and profits Then

what is the max print speed? thanks for your help

Electronics Forum | Mon Nov 05 13:33:08 EST 2007 | slthomas

Heck no, I mean we print relatively slower on complex boards, as in 1 inch/sec (25.4mm/sec), and maybe 2 inches/sec. (51mm/sec) on less complex boards. SMT is not a bottleneck in our plant and printing never the bottleneck in SMT, so I see no need t

Downtime Calculation

Electronics Forum | Sat Aug 17 18:41:29 EDT 2002 | kenbliss

Hi Brian Thank you very much for you comments, Points well taken, forgive the length of my response here, but I wanted to respond to each of your points. The Pick and Place machine �should� be the bottleneck. The reason is in my 20 years in the in

Time To Inspect

Electronics Forum | Wed Jun 20 16:09:21 EDT 2001 | Gil Zweig

Clearly, x-ray inspection should not become a bottleneck in the production process. The concept of "signature" identification is to rapidly qualify a BGA attachment as acceptable or suspicious. If suspicious, the board is taken off line for further s

What Else Are They Good For?

Electronics Forum | Tue Jun 19 17:56:04 EDT 2001 | genny

We don't currently use BGA's on any of our products. Are there other worthwhile reasons to use x-ray that would benefit enough from it to justify it economically? Also, I have heard that to put it inline can cause bottlenecks.

Production Line Setup

Electronics Forum | Wed Jun 19 04:54:45 EDT 2002 | ianchan

Nuez : u mean u put an operator to check the placement mounting of components, juz before the PCBA enters the reflow oven? how does that release the bottlenecks for efficiency rates? pls explain, coz we want to learn from your experiences. Thanks.

How long can you leave paste - update

Electronics Forum | Mon Apr 02 10:37:25 EDT 2007 | chrissieneale

I totally agree, if there is a bottleneck in the process anywhere then i think it's got to be hand fit, so that shoudl be driving the demand for the rest of the process. I need to time/measure things to prove it though. Great Monday discovery! :)

  1 2 3 4 5 6 7 8 9 Next

bottleneck searches for Companies, Equipment, Machines, Suppliers & Information

Voidless Reflow Soldering

High Resolution Fast Speed Industrial Cameras.
ISVI High Resolution Fast Speed Industrial Cameras

Nozzles, Feeders, Spare Parts - Siemens, Fuji, Juki, Yamaha, etc...
thru hole soldering and selective soldering needs

High Throughput Reflow Oven


"回流焊炉"