Electronics Forum | Thu Apr 28 15:56:44 EDT 2005 | stepheniii
Hopefully it is just the part data a little bit off. But if that doesn't help, make sure the thickness sensor is calibrated bang on. And do the nozzle height adjustment. What are your nozzles and filters like, as far as being clean goes? I've put dow
Electronics Forum | Tue May 03 15:19:12 EDT 2005 | cuculi54986@yahoo.com
Thanks for the suggestions. We have been going around the dome to pick from the base. The placement machines are Panasonic chipshooters - MV2VB and MV2C. I have several problems with the MV2C. The K-type feeder plates were moved by my predeces
Electronics Forum | Thu Dec 14 21:10:42 EST 2000 | Jeff
elfego, i used to wwork at a place with the following line layout: * Loader * MPM Hi-E * Triscan Solder Inspection Machine (affectionately called the "Trashcan" by the technicians ;-) * 2 Phillips FCM fast chip mounters * 1 Phillips Topaz "hybrid" (
Electronics Forum | Thu Mar 03 12:55:31 EST 2005 | dru_wells
We seek the following. Any referrals would be appreciated. Responsible for the complete development of unique feeders that present custom metal stampings and connector products for pickup by industry standard placement machines. The parts will be i
Electronics Forum | Wed Mar 21 11:52:56 EDT 2007 | slthomas
Mark, the only Panasonics I've worked with were MSHIIs and an MPAV2B and at this point I'm foggy on both, but both tracked component inspection errors quite well. You should be able to tell how many parts are rejected for thickness inspection errors
Electronics Forum | Wed Apr 23 17:33:54 EDT 2008 | pima
so what period of times are you loosing for changeover? is it half of hour? more or less? because I think that should also be a useful indicator, how much time does it take to switch to different product if we are using panasonic,universal,fuji,phili
Electronics Forum | Wed Dec 09 17:22:09 EST 2015 | tombstonesmt
I couldn't be more pleased with Panasonic. We've upgraded from MPAV's and MSR's to CM602/DT401 and now their NPM platform. NPM's are extremely fast and accurate. Their auto pickup position teach is great especially if you're running any 0402 2mm pit
Electronics Forum | Wed Mar 21 13:39:11 EDT 2018 | tombstonesmt
I know this isn't a choice from what I'm reading, but we use to kill LED boards with an old Panasonic MSR. Our newer CM-602 and NPM could not beat the speed when you're talking about a max of 3 different part numbers; depending on binning. My .02 .
Electronics Forum | Thu Jan 03 15:53:28 EST 2019 | cbeneat
We did figure out the issue. The plastic cover inside the LED lighting unit had a slight film covering it, which made the picture slightly hazy. We had to disassemble the LED module to get at it, cleaned it and it was fine. I didn't think this would
Electronics Forum | Wed Mar 29 03:14:43 EDT 2023 | frankchan
SMTXTRA as SMTEXTRA in UK? Susan? I know for a fact they are solid as we and some peer companies are suppliers of them for machine parts, feeders; nozzles, and calibration Jigs, even though our major business is with mounters and ovens, but no busine