Electronics Forum | Sun Feb 10 19:42:49 EST 2013 | gwego
anybody can share if there are publications/whitepaper relating how SMT Change-over is Measured? thanks in advance
Electronics Forum | Mon Feb 04 08:38:26 EST 2013 | cyber_wolf
Changeover starts when the last board from the work order goes into the reflow oven.
Electronics Forum | Sun Feb 03 23:06:23 EST 2013 | gwego
how do you measure the overall change over time of an smt line? where does it starts and end? lets standardize
Electronics Forum | Fri Dec 08 21:36:42 EST 2000 | reg
Hi everyone!! I have less than one year in the US, and I had been working as a field smt engineer. I have almost two years of experience as a manufacturing engineer, but what I really would like to do is process engineering. Can somebody advice
Electronics Forum | Tue Feb 26 08:52:35 EST 2013 | stephendo
Do you also measure job run time? IF you don't I"m sure if the change over time is measured but not the run time then the run time will go up almost as much as the change over time goes down.
Electronics Forum | Tue Feb 26 09:07:12 EST 2013 | emeto
Stephen, Changeover is the time we are not running the line, but we are changing for another product. Job run on the other hand depends on the quantity you have to build. For some manufacturers running the job will take weeks or months. For other it
Electronics Forum | Tue Feb 26 11:19:31 EST 2013 | anton99
Stephen, That's true and I am going to include the reflow time in our changeovers. That way if its taking to long to change the oven temperature it will show up in our metrics. I agree, if we miss a step in the changeover process our metrics will be
Electronics Forum | Mon Feb 04 08:52:28 EST 2013 | markhoch
Agreed, and stops when the first completed PCB of the next run goes in the oven. After 1st piece verification.
Electronics Forum | Mon Feb 04 22:42:59 EST 2013 | gwego
Thanks a lot. btw, is there a standard for this measure or technical paper to where we can base?
Electronics Forum | Fri Feb 22 03:53:11 EST 2013 | gwego
Hi Frazzled Man,did you mean this way? end - 1st piece of product "B" goes into the oven after 1st piece verification. does 1st piece of product "B" means it is the second piece of Product "B"
Main Products: 1. Original new and Original Used SMT/AI Spare Parts. 2. SMT Equipments And Related Machine( SMT Calibration, SMT Feeder Carts,Conveyer etc.) 3. Maintenace and Repair Service Pre-Sales Service Provide details ab
Manufacturer's Representative / Manufacturer / Equipment Dealer / Broker / Auctions / Consultant / Service Provider
Building A, Jiepeng Square, Fuyong
Shenzhen, 30 China
Phone: 0755-33578694